VS infrastructure project exceeds half-way point

Tom Savage/For the Journal
Valley Drive at Southside Drive facing north shows a newly paved road in Valley Springs on Tuesday, Aug. 3.
It’s been a summer of road construction in Valley Springs, but there’s light at the end of the tunnel.
A large-scale infrastructure project that has been split up into four phases is past the halfway point, and the entire project is on pace to be completed late next month, according to project engineer Gabe Laber of Omaha-based HDR Engineering.
Phase I from the lagoons down Cliff Avenue is complete. Phase II, which encompasses Valley Drive, is also close to being finished, as pavement has already been put down. Phases III and IV will ramp up soon, which includes Cliff Avenue and Dunham Street to Broadway.
Mayor Carl Moss said he was hoping the entire project would be completed by October, but Laber said the project is ahead of schedule.
“You hate to make any promises, but they’re on track to be done before the completion date,” Laber said. “We’re over halfway done and it’s gone pretty smooth.”
Laber said the project received a big break this year with the weather. In 2019, several construction projects in the region were delayed several months, if not into the following season, with a deluge of wet weather.
“It’s been unfortunate for the farmers, but a dry year helps out contractors because rain really slows them up,” Laber said. “Putting the underground pipe in is really the critical path and they’ve done a good job of getting that done. The weather has helped.”
As with any construction project, headaches are sure to follow. It’s been an inconvenience for several Valley Springs residents as streets have been inaccessible since just before the school year ended in May. New sewer lines have resulted in the complete deconstruction of the roadways.
Despite the upheaval, Valley Springs residents seem to be taking it in stride. Carmen Ruhlman has lived in the community for 18 years, and she said the inconvenience is going to be worth it.
“We’ve had problems in the past when we get a large amount of rain in a short amount of time. I absolutely think one summer of pain is worth it in the long run,” she said. “Valley Springs is just continuing to grow so in order to support that growth, we have to really support the infrastructure improvements that they’re making.”
Moss said residents have been understanding, but they’ve received a few phone calls regarding water discoloration after lines were turned back on. The process includes putting in a temporary water line while crews install the new infrastructure. That process kept some residents unable to have water for “four to five hours” while crews made the switch from temporary to permanent. Once the permanent lines are established and flushed out, discoloration can occur.
Moss said that the process is normal and water flow returned to its routine state after a short period.
“People let us know when it happened and we told them it was normal,” he said of the water issue. “Everybody’s been really cooperative and understanding. It’s inconvenienced some people, but hopefully when we get done everybody will appreciate it.”
Before the project began, Laber and his team held a public meeting for the Valley Springs community. He said he’s learned over the years to set expectations upfront to let residents understand the process and that there will be some discontent along the way.
At that meeting, he told the collective group that things always get worse before they get better, and to have patience.
He said so far, everyone in Valley Springs has been tolerant of the project.
“Everybody’s patience is fine in April, May and June. But as the summer wears on, patience starts to wear thinner and thinner,” he said. “Two of the phases are paved, so at least people aren’t dealing with a torn-up street all summer, and that’s helped, too. But it’s always an inconvenience. I haven’t gotten chewed out yet, but it is still early August.”