City to enlighten public on core area reconstruction
By:
Jill Meier, Journal editor
Project leaders seek input with online survey
Fact: The roads and infrastructure in Brandon’s core area have long out-lived their useful life.
Fact: The roads and infrastructure in Brandon’s core area will be replaced starting next year.
Fact: The core area reconstruction project will occur over the next four to five years, and property owners are sure to be inconvenienced at some point during the process.
Fact: Property owners in the core area can learn about all of the above at an open house from 4 to 7 p.m. Thursday at Brandon Valley Assembly of God.
“There are many facets to the project and the city wants the public to be aware of what’s planned,” said HDR project manager Paul Sanow. The project encompasses every block between Holly and Aspen boulevards and Sioux to Splitrock boulevards and affects about 1,500 residents who live in that area.
Sanow went on to explain the core area – constructed between the 1950s and 1970s – will not only receive new road surfacing, but new utilities (water and sewer lines, sewer mains, sanitary sewer) and possibly, the addition of sidewalks for increased community access and connectivity. The open house is intended to provide information and gather feedback on the project.
The project is currently in the design phase and all comments and feedback received will be considered in the project’s design. Public input is being gathered through an online study, which is available at https://www.surveymonkey.com/r/BrandonCore.
Over the last 10 years, Brandon residents have seen similar work done in the Sylvan-Rushmore area.
“It’s a pretty standard residential project with the exception of a few potential changes that we did not do in those areas,” Sanow said. “There’s water mains and sanitary sewer that needs to be replaced. I think some of that area is even in the water-trickling area, so for the city’s sake when we put the new water main in, we’ll make sure that it is at that standard six-feet depth for the water service.”
Property owners who wish to replace water lines from the curb stop to their homee, will have the option to do so, Sanow said.
“Typically, if homeowners are having problems with their sewer services, the city will replace it up to the property line and from there the property owner has the opportunity to replace it to their home (at their cost),” he adds.
Mayor Paul Lundberg wants constituents to know the project has been on the city’s “to do” list for years.
“This is not a project that just came up with the advent of Tim Jorgenson or Paul Lundberg being on the council. It’s a project that’s been on the books for a lot of years and now it’s coming to fruition,” Lundberg said.
The most visible of needed repairs is the roads.
“If you did a life cycle analysis of the existing asphalt that is there now, it’s pretty much shot. It’s long outlived that life and it was not built according to our existing standards,” he said.
The core area’s existing water main was also not built to current standards, and Sanow informs there have been well-documented water main breaks in this general vicinity.
Timeline
The massive reconstruction project will begin on the west side of the core and will be done in four to five phases. The first phase will be bid in early 2020.
“The city is being pretty aggressive in the amount of work that they want to get done every year,” Sanow said. “When the requests for proposals initially came out, the goal was to be done in 2025, and so that’s five years’ worth of construction and about 36,000 feet – approximately 70 blocks of construction. From a scale size of the project, it’s quite a bit bigger than the projects we were doing in Sylvan Circle.”
Sanow explained project phases will be based on utilities.
“Naturally, it has drainage basins where we have to start at the bottom and work our way up, and some of that is based on budget funding for these projects, too. We can stop in a logical location where when we can design it and do the cost estimation of it, and if it looks like it’s going to be bigger than what the city can budget or fund, we can cut things back,” he said. “The other thing that we want to talk about is we’ll try to phase those projects. We will have phase 1A, phase 1B, maybe even phase 1C, where we’re not allowing the contractor to just go in there and tear out the whole neighborhood. We’ll break it up.”
Lundberg said the work being done at the Holly and Sioux boulevards intersection needed to be addressed before reconstruction of the core area can begin.
“Nothing could happen until that got done. That’s really phase one of the whole thing, to get the interceptor in,” Lundberg said.
Storm sewer is also being tied into the reconstruction endeavors. Sanow said it’s important that the storm sewer is tied in to improve the storm sewer system. Those improvements include the sanitary sewer, water main, storm sewer, and drainage improvements.
“We will take a look at all of the areas that have drainage issues and try to take care of those,” he said.
Valley gutters, which are necessary to through an intersection, will be included in the design.
Sidewalks
Although a large chunk of the core area does not have sidewalks, city administration is placing a heavy emphasis on adding those into the design process.
“When the city wrote the request for proposal, it was pretty clear that sidewalks are a key component of that project,” Sanow said. “We look at connectivity within the community and we always discuss safety. This area, especially with the connections to the schools and the park, becomes something the city should take a look at.”
Lundberg and city engineer Tami Jansma both said several homeowners have expressed their dissatisfaction to the idea.
“From the Mayor’s chair, from Tim Jorgenson’s chair, sidewalks are a key component of this whole project. It’s got to happen,” Lundberg said. “This place is going to be demoed, it’s going to be demolished and it would be irresponsible on the part of a city council or a city, in general, to not seriously look at the sidewalk issue in that area.”
Sanow went on to explain the proposal also takes a look at shared use paths.
“We currently have them on Holly and Aspen, and so adding a connection between Holly and Aspen with a shared-use path through that core area is in one of those phases. We’ve also talked about Fourth Avenue and Sixth Avenue. Fourth has a pedestrian crossing on Holly and Sixth Avenue has a controlled intersection, so from a logistics standpoint, those two locations make sense,” Sanow said.
It’s likely the shared use paths would be paid for and maintained by the city, not the property owner, he added.
Sidewalks are also a Brandon standard now.
“New developments are required to have sidewalks, and this is one of three neighborhoods out of 15 to 20 neighborhoods that doesn’t have sidewalks,” Sanow said.
Lundberg stressed that no firm decision has been made on sidewalks yet.
“The committee has discussed all options, and as with anything, there’s whatever number of committee members, there’s that many opinions. What we have to be careful of as city leaders is not to get caught up in the ‘muck,’ and what I mean by that is we have to look down the road, look at the whole project. We can’t get caught up in the detail if a tree is going to be able to stay there,” Lundberg said.
Narrower streets
Streets in the core area are also expected to narrow from 37 feet to 33 feet, which is the standard size for residential streets, Sanow said.
“Whether there’s parking on one side or both sides, the function of that traffic driving down that street doesn’t necessarily change,” he said. “For the most part, when people drive through residential areas, they’ll stop and let a car drive through that area whenever you have cars parked on both sides.”
Narrowing the streets – built with more gravel and thicker asphalt – equates to approximately $800,000 less in construction costs.
“That’s just the upfront savings,” Sanow said. “It’s also less money and time for the city to maintain long-term.”
Lundberg said the core reconstruction committee is looking to reinvest that savings into a higher-quality road system
“We’re reinvesting to make a better product for the 33 feet that remain would be the idea behind that,” he said.
Public meeting
At Thursday’s public meeting, there will be stations set up for property owners to gather information and view the geometrics of the project.
Sanow reminds the project design is still very preliminary.
“We haven’t gone through any grades, we haven’t looked at any elevations. We’re just getting the survey wrapped up because it’s key that we keep moving on these decisions so that we don’t delay the project,” he said.
The public will also learn about a citywide drainage plan study Thursday, and feedback from an online survey is needed. The master drainage plan will incorporate the core reconstruction design.
There will also be information on low impact design that will essentially allow more water to soak into the ground rather than drain into the storm sewer.
“We also have potential retention pond locations. One is south of Brandon Elementary, and there’s other ideas, like rock landscaping or drainage channels that have some infiltration, too, so that xeriscaping is just one element,” Sanow said.
Jansma said xeriscaping has generated interest from the public but design standards are needed first.
“There will be a little bit of trial and error and we’ll have the city do some of those test projects to figure that out first,” she said.
“There’s a lot to xeriscaping and there’s a lot to low-impact design and most of it has to do with getting more water into the ground and less water into the storm sewer, essentially, and requiring less water to maintain,” Alderman Tim Jorgenson said.
“These projects are a long process. The city has done a really good job of looking at the residential streets and trying to prioritize these projects. As we’re moving through the core area, the construction of these and lack of access at times during construction is going to be part of the projects, but I think most people realize that the roads need to be updated, the utilities need to be updated,” Sanow said.
“I’m proud that we’re doing this because most municipalities aren’t focused this much on infrastructure, especially old infrastructure, and we’re doing it, which is kind of cool,” Jorgenson summed up.
To learn more, contact Paul Sanow, HDR project manager, at 977-7756 or 400-5764, or by email, Paul.Sanow@hdrinc.com, or Tami Jansma, city engineer, at 582-6515, extension 4, or 679-0129 or by email, tjansma@cityofbrandon.org.