Water committee suggests system changes
By:
Jamie Hult, Staff writer
Recommendations to city council include removing well 7 radium, future water softening
After months of research and multiple rounds of reviews, Brandon’s water development committee has decided what it thinks the city should do about its water.
At the Aug. 19 city council meeting, Del DeBoer with AE2S, the engineering firm hired to conduct a thorough study of Brandon’s water system, reported the water committee’s recommendations.
The committee made its recommendations from a long list of options proposed by AE2S regarding the city’s water sources, infrastructure and processes.
The committee’s recommendations are suggestions presented to the city council. The council will look at approving any or all of them at an upcoming meeting.
The water development committee’s recommendations include:
• Relying on the city’s current well water sources rather than contracting with Minnehaha Development Water Corp., which has stated it can supplement Brandon’s short-term supply;
• Add WRT Radium Removal to treat well 7 and conduct further testing before incorporating the well into the city’s water system;
• Connect well 3, the city’s backup water source, to the water treatment plant;
• Conducting additional research on Splitrock Creek’s water supply potential;
• Expanding Brandon’s water treatment plant, a plan that’s already in the works;
• Securing additional water rights in the Splitrock and Big Sioux aquifers; and
• Consider adding RO (Reverse Osmosis) treatment at the plant in the future to lower the amount of TDS (Total Dissolved Solids) and create softer water.
DeBoer advised the council on considering these recommendations.
“Your opportunity as a city council is to think about how this will be phased,” he said, in addition to how the recommendations will affect customers’ water rates.
He estimated the recommendations would run $1.5 million in capital costs, and rates would rise around 30 percent if the city opted for RO and softer water.
Alderwoman Barb Fish suggested the city consider holding a public media campaign on using well 7. Purchased from Sioux Falls and found to be high in radium, the well has been sitting idle for around two years.
“We will not jeopardize the safety of our citizens,” assured city administrator Bryan Read. “We will make the parameters very safe to determine using well 7.”
Read said connecting well 3 to the treatment plant may create a bottleneck, as the plant is already at capacity.
“It may boil down to the core reconstruction,” he said, adding that the city would start looking at upgrading the treatment plant.
Investigating the Splitrock Creek aquifer for more well sites could prove beneficial, DeBoer said.
“There are some unknowns in the Splitrock Creek aquifer. It’s one more step just to assess if it’s an appropriate water source,” he explained.
The city council accepted AE2S’s report and the water committee’s recommendations. They did not set a date for addressing them at a future meeting.
The council convenes next at 6 p.m. Tuesday, Sept. 3, in council chambers.